Contractor's Performance Must be Workmanlike
by James R. Keller
This article appeared in St. Louis Construction News &
Review, p. 11, November-December, 2003.
Contractors must perform their work, including the selection
of materials, in a workmanlike manner even when their contract does not cover
this requirement, a Missouri Court of Appeals for the Eastern District recently
reaffirmed. Workmanlike means work that
is "completed in a skillful manner and is non-defective." The case is Jones & Turner, Inc. and Woody Bogler Trucking Co. v. Elmer Senevey
and Eric Senevey b/d/a Elmer and Eric Senevey Construction Co., No. ED81853
(Mo. App.), decided September 16, 2003.
Construction contracts often specify in detail the
contractor's level of performance. Many
contracts, however, including the one in Jones,
do not set out the degree of skill and competence required of the
contractor. The Jones decision reemphasizes the importance to a contractor of
selecting proper materials and product to ensure that the work is indeed
workmanlike.
Jones & Turner and Woody Bogler Trucking were two
companies that needed a building to keep clay dry for their businesses. They described their needs to Senevey
Construction, a contractor, by saying they wanted a metal building that was
tall enough for trucks to fit inside, mobile so it could be moved when the clay
was depleted, and sturdy enough to last about ten to twelve years.
They entered into a written contract for Senevey
Construction to construct such a building for $28,500. They later increased the contract price to
$29,000 with a slight change in the scope of the work to make the building a
little taller and wider.
To achieve the scope of work, Senevey Construction purchased
a "building kit" for the building from Moniteau Machine & Manufacturing,
Inc. Senevey had never before purchased
a kit from Moniteau.
The contract included specifications that required: "Pour a
5' wall 8" thick with a 2' dead man at each truss leg, setting on a 8"
footing. The two end walls will be
completely open. Sides will have tin
14' down from the top. On your level
lot."
The building kit arrived without any plans. Representatives of Moniteau, upon inquiry,
informed Senevey Construction that plans were not needed. Based upon this information, Senevey
proceeded to assemble the building, without plans, in a manner it thought was
correct.
In addition to no plans, the kit was missing important
materials, including bolts needed to attach the trusses, angled sheeting for
the side walls and trim sheeting for the roof.
Senevey obtained substitute materials from various sources to complete
the job. In at least one instance,
Senevey deviated from the kit in order to solve a particular problem that arose
during construction.
Senevey completed the building and the two businesses paid
Senevey in full for its work. About
four months later, on January 1, 1999, four inches of snow with some ice fell
onto the building. The next day the
building collapsed in the center.
The building could not be salvaged. The two businesses hired Roger Verslues, a
licensed engineer, to inspect the collapsed building and determine what went
wrong.
Verslues obtained a set of plans for the building from the
engineering company that had originally prepared the plans. An engineer from that company testified at
the trial that he discovered considerable differences between the sizes of
material called for in the plans as compared to the actual building kit
provided by Moniteau.
In addition, Verslues observed two to three significant
deviations from the plans that affected the structural stability of the
building. He noted about ten total
deviations between the plans and the building's as-built condition.
The businesses sued Senevey; Senevey sued Moniteau but then
later dismissed Moniteau without prejudice from the case. The trial judge-there was no jury-found in
favor of the two businesses and awarded the full contract amount of $29,000
plus costs.
Senevey argued on appeal that there is no implied warranty
for a building that is attached to the land and that the trial court had
specifically stated that Senevey did nothing wrong in putting the building kit
together. The appellate court rejected
these arguments and held that "the law imbues construction contracts with an
implied warranty to perform the work in a workmanlike manner."
The court concluded that Senevey's work was not
workmanlike. The building kit that
Senevey chose, the court decided, was inadequate, as evidenced by a collapsed
building only a few months after construction.
Significantly, the appellate court focused on an inferior product rather
than poor construction.
Contractors assume enormous responsibilities when they agree
to build something. As this case shows,
it often is the contractor's selection of materials more than its construction
techniques that leads to problems.
James R. Keller is a partner at Herzog, Crebs & McGhee,
LLP, St. Louis, MO, where he concentrates on business litigation, construction
law and ADR. He also is an arbitrator
with the American Arbitration Association and a mediator.