Recent Construction Cases Lengthen Time to Sue
by James R. Keller
This article appeared in St. Louis Lawyer, p. 9, February 4,
2004.
In three
important decisions since 1999, Missouri's appellate courts have expanded the
time for filing construction lawsuits against contractors, engineers and
architects even though the plaintiff owners in each were aware early on of
certain construction problems. The
cases set a clear direction in how courts will examine statute of limitations
defenses and the circumstances when a lawsuit can be maintained more than five
years after first learning of some type of construction defect or failure.
This Article
will examine these three cases.
Business Men's Assurance Co. of America v. Graham
The first
case is Business Men's Assurance Co. of
America v. Graham, 984 S.W.2d 501 (Mo. 1999). The Missouri Supreme Court decided that architects and engineers
can be responsible for defects 39 years after construction. The decision cost the architects/engineers
$5,287,991 in jury-awarded damages.
In 1960,
Business Men's Assurance (BMA) contracted with an architectural and engineering
firm (Skidmore, Owings & Merrill) to design the BMA office tower in Kansas
City, Missouri. Construction started in
1961 and ended in 1963.
The
building's exterior contained more than 4.000 panels of marble that were each
1" thick and covered all four sides of the building's vertical columns. Metal anchors attached the marble panels to
the building.
The contract
provided that Skidmore would use its "best efforts" to supervise and protect
the owner against defects but Skidmore did not guarantee the contractor's
performance.
In 1985, one
marble column panel fell from the penthouse to the tower. A month later, two horizontal panels fell
seven stories to the ground.
BMA hired
Black & Veatch to investigate.
Black & Veatch discovered significant design problems, including a
finding that at least 25 percent of the anchors were either missing or were of
an incorrect type and that all of them were 1/16" thick instead of the
specified 1/8".
Black &
Veatch further found that the marble failed to meet industry standards for the
early 1960's. Over the years, the
marble warped, cracked and lost strength.
In 1986, the
owners sued Skidmore and others for negligence and breach of contract, which
prompted a settlement from everyone except Skidmore. During the litigation, Skidmore argued that the owner waited too
long to sue, pursuant to Missouri's statute of limitations, 516.100 R.S.Mo.,
a statute long disputed as to its meaning and reach.
Section
516.100 provides in part that "the cause of action shall not be deemed to
accrue when the wrong is done or the technical breach of contract or duty
occurs, but when the damage resulting therefrom is sustained and is capable of
ascertainment, and, if more than one item of damage, then the last item, so
that all resulting damage may be recovered, and full and complete relief
obtained."
A claim for
breach of contract under Missouri statutory law must be brought within five
years. 516.120. The question is within five years of
"what." No Missouri case has ever
clearly or precisely defined what "sustained and capable of ascertainment"
means or how it is to be applied, despite hundreds of cases that have involved
this phrase. See Business Men's at
139.
At trial,
Skidmore introduced evidence that the owner knew of early problems with the
marble. Apparently, the marble pieces
chipped off and had to be reattached.
One panel was replaced and in 1975 the entire exterior of the building
was recaulked.
The Missouri
Supreme Court decided that these early problems were not significant enough,
legally speaking, to alert BMA that the system as a whole was defective. Such knowledge did not occur until 1985,
when the panels began to fall. The
Court separated damages involving less important elements of construction from
later damages that involved more serious and expensive repairs.
Allen v. Kuehnle and Kuehnle Bros. Constr. Co.
The next case
is Allen v. Kuehnle and Kuehnle Bros.
Constr. Co., 92 S.W.3d 135 (Mo. App. E.D. 2002). The Eastern District Court of Appeals decided that a homeowner
could sue her contractor seven years after moving into the house. Minor punch-list items immediately after construction
were not enough to trigger an earlier date.
The Court
decided that Missouri's five-year statute of limitations for breach of contract
did not start until the homeowner knew of serious structural defects. This case lengthens the potential exposure
and liability of contractors.
The
contractor was to build a new house that would occupy a quarter of the
"footprint" of ground excavated by the contractor during removal of the prior
house. After moving into the completed
home in May 1993, the homeowner noticed various problems, prompting a punch
list dated August 24, 1993.
The punch
list contained 26 items including hairline cracks in the drywall, drywall tape
pulling away from walls in certain places, two sections of the sidewalk that
sloped, and some loose shingles. The
contractor repaired or attempted to repair most of the items on the punch list.
In 1998, the
homeowner began to notice "numerous new, more dramatic problems with her home,"
such as cracks in the foundation and exterior brick walls, a huge L-shaped
crack in the family room, and drywall tape that was pulling away from the walls
in nearly every room.
The homeowner
decided to have her home piered, per an engineer's advice. This process generated considerable dust and
debris. While cleaning the dust, the
homeowner developed a sore on her foot that became infected, resulting in a
hospital stay and medical costs of $3,667.
Allen sued in
November 1999, claiming breach of contract and negligence and sought a
rescission of the contract. The
contractor defended, to a considerable degree, on the grounds that Allen had
waited too long to sue.
The issue was
whether the punch list created in 1993 and the homeowner's knowledge about
problems before 1995 were enough to provide notice to the homeowner of the
structural problems. There was
contradictory evidence on this point.
The
contractor had argued that the homeowner knew of structural problems more than
five years before she filed the lawsuit.
The trial judge agreed and granted summary judgment for the contractor.
The appellate
court relied heavily on the decision in Business
Men's Assurance Co. of America v. Graham.
The court concluded that material facts were still in dispute as to when
structural problems were ascertainable; thus, the trial judge erred by granting
the motion for summary judgment.
In
distinguishing other cases, the appellate court found the compelling difference
to be that the homeowner's problems before 1998 were not problems related to
settlement or faulty soil compaction.
Rather, the prior problems were typical, common issues experienced
during the construction of a new home.
Loeffler v. City of O'Fallon
The third
case is Loeffler v. City of O'Fallon,
71 S.W.3d 638 (Mo. App. E.D. 2002). The
Eastern District decided that an owner could sue the City of O'Fallon more than
five years after completion of a project and after first noticing construction
defects. The result should prompt
contractors to reconsider whether they will extend open-ended offers and
agreements to remedy construction defects after completion.
Loeffler, the
homeowner, had sued the City of O'Fallon for breach of contract. While the record is not precisely clear, it
appears that the City was doing some construction work and needed a temporary
construction easement for access to the homeowner's property.
The contract
included handwritten "special conditions" that provided the City would be
responsible for and promptly correct any water backup or other problems due to
construction. The City's
responsibilities did not expire upon completion of the project.
The City
completed the project in May 1992 and thereafter the homeowner noticed grading
changes and poor drainage from the fall of 1992 through the spring of
1993. In 1993, she notified the City
that her yard was sinking. This was
more than five years before she eventually sued.
During the
next two years, Loeffler's property sustained damage due to poor drainage
including wall fractures and moisture intrusion into the basement. In March 1994, she obtained and sent to the
City a bid from a grading contractor to correct the drainage problem.
In August
1994, the City's insurance company sent Loeffler a response denying liability
but adding that it would re-evaluate if Loeffler produced documents to support
her claim. Loeffler filed her lawsuit
in June 1999. This was more than five
years after obtaining the bid for corrective work but less than five years from
first hearing that the City through its insurance company denied
liability.
The City
convinced the trial court that Loeffler had waited too long to sue since
Loeffler's property clearly had damage that she knew about in 1993. In reversing the trial court, the appellate
court decided that the City had contractually agreed to fix any defects after
construction and had not limited the period of time to do so.
Loeffler was
required to offer the City an opportunity to correct any defects before filing
the lawsuit. Thus, the appellate court
concluded that the statute of limitations did not begin to run until the City
first refused to be responsible for problems resulting from its work.
In reaching
this result, the appellate court recognized a "line of cases which stand for
the proposition that, in certain instances, a plaintiff need not give a
defendant an opportunity to correct defects."
Id. at 643. The court did not believe it had to follow
them because they contained contract provisions different from the one between
the City and Loeffler.
About the Author
James R. Keller is a partner at Herzog, Crebs & McGhee,
LLP, where he concentrates his practice on complex business litigation,
construction law and ADR. He is the
Co-Chair of BAMSL's Construction Law Committee, Chair of the Construction
Advisory Committee of the American Arbitration Association (AAA), St. Louis
Region, and Vice-Chair of the ADR Committee of the Missouri Bar. He also is the legal writer for the St.
Louis Construction News & Review, an arbitrator with AAA and a mediator in
lawsuits in federal and state courts.