Subcontractor recovers $220,435 from General Contractor on Oral Contract
by James R. Keller
This article appeared in St. Louis Construction News &
Review, p. 21, July-August, 2004.
Missouri's Western District Court of Appeals recently
affirmed a trial court's decision that subcontractor KC Excavating and Grading,
Inc. could recover $220,435 from its general contractor Crane Construction
Company for breach of an oral contract.
The court looked to KC's bid, the plans and specifications and Crane's
letter of acceptance in determining what they had agreed to do.
The case is KC
Excavating and Grading, Inc. v. Crane Construction Company, No. WD 62271,
decided June 29, 2004.
Construction projects frequently proceed on the basis of an
oral conversation and a handshake. In
fact, some contractors and subcontractors view the request for a written
contract to be a showing of distrust.
Others are in a hurry to get started and consider the process of
obtaining an executed written contract to be an unnecessary delay.
This decision reinforces the need for written contacts to
avoid misunderstandings and disputes and reaffirms that oral contracts in
construction projects are enforceable.
Without a written contract, the parties are subject to the court's interpretation
of conflicting evidence as to the intentions of the subcontractor and the
general.
Further, a judge's decision on such evidence will not be
overturned on appeal absent an abuse of discretion by the trial court-a high
standard to prove and overcome.
In this case, KC had not signed Crane's proposed written
agreement, which KC asserted at trial it never received. The parties proceeded on the project based
on an oral agreement, defined by KC's written bid, the plans and specifications
and Crane's letter of acceptance of KC's bid.
The project was a building site in Warrensburg owned by the
trust of William Koch and Phyllis Koch.
The dispute started in 1997 when KC decided the contract documents did
not specify properly the scope of KC's work and that KC would have to excavate
more dirt than the contract documents required.
In response, Crane concluded that KC was not working fast
enough to stay on schedule. Crane
demanded that KC provide written assurances
that it would perform its work on time. KC did not provide such assurances.
Crane told KC not to continue its work until the dispute was
resolved. Within one week, Crane
terminated its contract with KC and obtained a replacement contractor to
complete the excavation.
By then, however, KC had excavated 35,000 cubic yards of
dirt beyond the specified contract documents.
KC spread most of the dirt over the property at Crane's direction and
stockpiled the rest for removal.
Crane did not pay for any of KC's work in excavating the
35,000 cubic yards of dirt. KC filed a
mechanic's lien on the property and filed a lawsuit to enforce its lien,
seeking damages from Crane for breach of contract.
Crane argued that KC was required to be on the job site
during certain hours, attend to its burn pits and aerate the soil on a
particular schedule. Even if this were
true, the appellate court concluded that these failures were not material to
the contract and thus they could not create a reason for Crane not to honor the
contract.
KC's written bid called for structural excavation and
backfill but was contingent on KC doing the total site-grading package. Crane interpreted this to mean all such work
would be for the contract's lump-sum price of $98,297.
The trial and appellate courts, however, decided that a
reference to "unit prices" in the contract documents referred to additional
work not covered in the plans and specifications. Thus, the parties agreed to a separate method of payment for such
work-on a unit price basis-and this work was beyond the contract's original
lump-sum price.
The court concluded that KC was entitled to recover $220,435
for such additional excavation work.
Crane also argued that based on past occasions a change
order was required for the additional excavation work. Rejecting this argument, the court reasoned
that even if this were true, the absence of a change order in this case did not
preclude KC's recovery because parties can waive the requirement of a change
order by orally agreeing to do the work and to pay for it.
Evidence during trial showed that Crane's superintendent
told KC to do the additional excavation work and a change order would
follow. The court decided that this
created an enforceable oral agreement and a waiver of the contract's
requirement for a change order.
James R. Keller is a partner at Herzog Crebs LLP, where he
concentrates his legal practice on complex business litigation, construction
law and alternative dispute resolution.
He also is an arbitrator with the American Arbitration Association and a
mediator.