Contractor Loses $450,000 Recovery Due to Lack of Documentation
Contractor Loses $450,000 Recovery Due to Lack of Documentation
by James R. Keller
This article appeared in St.
Louis Construction News & Review, p. 13, March-April, 2001.
In a contractor's lawsuit against an owner,
Missouri's appellate court in Kansas City recently upheld a trial judge's
decision to take away a jury verdict of $454,572 under Missouri's Prompt
Payment Act. The case is a good example
of how important it is for a contractor to properly document its claim if it
expects to recover interest for late payments.
The appellate court
also reversed a judgment in favor of the contractor for breach of contract for
$561,200 and sent this part back for another trial. The case is Environmental
Protection, Inspection and Consulting, Inc. v. City of Kansas City, Missouri,
WD56182 (decided December 26, 2000).
In 1992,
Environmental Protection, Inspection, and Consulting, Inc. (EPIC) contracted
for $400,000 with the City of Kansas City (KCMo) to build a replacement
spillway at the Kansas City Zoo. This
was part of a $50,000,000 Zoo renovation.
In 1998, a Kansas
City jury awarded EPIC the $454,572, plus another $40,000 for negligent
maintenance of property and $561,200 for breach of contract. KCMo, the defendant, was looking at an
adverse judgement of $1,055,772.
This is when things
started going bad, lawsuit wise, for EPIC.
First, the trial
judge set aside the jury's interest award of $454,572. Then on December 26, 2000, Missouri's Court
of Appeals in Kansas City threw out the contract damage award of $561,200 based
on an error in the instruction to the jury and ordered another trial. The appellate court upheld the trial judge's
decision to deny the interest award.
EPIC will not get another chance at this claim.
This leaves EPIC,
after nine years, with a $40,000 recovery.
EPIC and KCMo now face another potentially long trial--the first one
went six weeks--to determine if EPIC can recover more on its claim for breach
of contract.
EPIC's claims arise
from an agreement with KCMo to build a new spillway, diverting water for the
first time to the Blue River. A prior
spillway channeled water to a lagoon.
The specifications called for building the spillway without draining the
lagoon. To do this, EPIC built a
cofferdam, a temporary structure using sheet pilling and concrete forms, to dam
the water and thus permit excavations for the spillway.
Water seeped under
the cofferdam. EPIC used pumps to
remove the water but eventually the water backed up so far that work on the
inlet excavation had to stop.
EPIC
determined that the water flowed through a specific layer of porous rock under
the cofferdam. KCMo ordered the rock's
removal. After the lawsuit was filed, EPIC learned that KCMo and its engineers
knew of the rock's existence but did not disclose it in the bid documents or
the contract.
Also, a
KCMo work crew filled a ditch near the existing spillway with dirt, causing the
water from a big rainfall to rise over the cofferdam and flood the new spillway
work site. The flood created the need
for extensive repairs and cleanup. EPIC
lost equipment and materials. (This is where the jury awarded EPIC $40,000 for
loss of its business concern due to these problems.)
KCMo urged
EPIC to timely complete the project, which required extra work. EPIC submitted change orders to cover what
happened, but KCMo only approved about $12,500 of them.
EPIC's bad
luck continued. The relationship
between EPIC and KCMo broke down. A
material supplier sued EPIC. The losses
on the project forced EPIC to go out of business in 1994, the same year it
filed this lawsuit.
EPIC sued
under Missouri's Public Works Prompt Payment Statute, which applies to
contracts with the government. It
promotes timely payment to contractors, subcontractors and suppliers and allows
them to recover 1.5% interest per month for late payments made in bad faith,
plus reasonable attorney fees. The
statute sets out many reasons an owner can withhold payment and not face this
interest charge, such as unsatisfactory work progress, defective work or
materials that are not corrected and disputed work.
The statute
requires the owner to pay the retainage to the contractor within 30 days after
the contract work is substantially complete and the public owner accepts. However, the contractor must submit its
invoice and all other appropriate documentation and certificates in complete
and acceptable form as required in the contract. Before final payment is due, the contractor also must file with
the owner all the documents and certificates required by the contract.
The trial
judge decided, and the appellate court agreed, that EPIC did not present any
evidence that it submitted to the owner the required invoice or the other
appropriate documentation and certificates as required in the contract and the
statute. Thus, the trial judge properly took away the jury's damage award on
this issue.
EPIC argued
that its change order requests, a certificate of completion and a payment
request were enough to comply with the statute's requirements. The appellate court decided, however, that
these facts may help EPIC on its breach of contract claim for extra work but
they were no substitute for what is required to trigger a prompt payment claim
under the original contract.
Even the
jury's finding that KCMo withheld payment in bad faith could not save this
claim. Compliance with the threshold
requirements of documentation is mandatory.
James R.
Keller is a partner at HERZOG, CREBS & McGHEE, LLP, St. Louis, Missouri,
where he concentrates on construction law, real estate and business
litigation. He is also a panelist with
the American Arbitration Association.
This
article originally appeared on page 13 of the ST. LOUIS CONSTRUCTION NEWS &
REVIEW/MARCH-APRIL 2001.