Missouri Judges Still Say: 'Show Me the Contract,'
Missouri Judges Still Say: "Show Me the Contract"
by James R. Keller
This article appeared in St. Louis Construction News &
Review, p. 16, July-August, 2001.
In the past few months, several appellate decisions in
Missouri send a clear message to the construction industry about the importance
of having a properly worded written contract.
Judges in the Show-Me State still ask:
"where's the written contract?" and "what does it say?"
More and more, construction contracts now contain written
provisions requiring dispute resolution through arbitration instead of
court. The wording of an agreement to
arbitrate can make all the difference, as Metro Demolition discovered in Metro
Demolition & B Excavating Company v. H.B.D. Contracting, Inc. and E.M.
Harris Construction, ED 76988 (ED Mo. 2001).
Metro, a subcontractor, and HBD, the general contractor,
entered into three written subcontracts for excavation and earthwork at the
Murphy Park Public housing project in the City of St. Louis. The subcontracts incorporated provisions
from the contract between the owner and the general contractor, including the
standard AIA provision in Article 4.5.1 of A201 that all claims must be settled
by arbitration with the American Arbitration Association.
The problem was in the timing of the subcontracts, for one
of them was dated before the owner and general had signed their own contract.
Missouri law allows contracting parties to incorporate by
reference into their written agreement provisions from other contracts. This is a common practice in
subcontracts. The appeals court in Metro
determined, however, that arbitration was not proper in the one subcontract
because the subcontract referenced an owner-general contractor contract that
did not yet legally exist.
This case points out the importance of subcontractors
verifying the contracts they incorporate by reference. Otherwise, the
incorporation may not be valid. In this
case Metro had to split its case by having a traditional trial on one of
its subcontracts and arbitration on the other two.
Another common practice is executing a release for payment
received. Many contractors and subcontractors sign such releases thinking that
they are merely acknowledging payment.
That is what Baker-Smith Sheet Metal, Inc. unsuccessfully
argued in Baker-Smith Sheet Metal, Inc. v. Building Erection Services
Company, WD 58946 (WD Mo. 2001).
Baker-Smith furnished BESCO, per a written contract, insulated metal
panels for the control tower at the Kansas City airport.
Baker-Smith made the panels per the shop drawings, but the
panels were too short. Baker-Smith
quoted a price of $10,555 to make another set of panels that BESCO then
ordered. BESCO paid Baker-Smith the
full original contract price (but not the additional $10,550).
Baker-Smith signed a release acknowledging payment in full
for all work through a certain date, which included the cost of the additional
panels. Baker-Smith sued to recover the
additional money and a jury awarded it $10,555 for this work.
The appeals court reversed, holding that the trial judge
should have overturned the jury's verdict based on the release. In fact, the court found the release to be
so clear that the trial judge erred by even allowing evidence of what
Baker-Smith intended when it signed the release.
In Bogdon Hiblovic v. Cinco-T.C., Inc., ED77401 (ED
Mo. 2001), the homeowner sued for breach of contract, alleging that the
contractor should have fixed a faulty foundation wall. Cinco-T.C. countered
that it had repaired the wall and had built a separate retaining wall at no
charge as part of a new oral agreement to resolve their dispute.
The contractor claimed that the judge erred by not allowing
the jury to consider this work to be an accord and satisfaction, a defense to
paying additional money. An accord is
an agreement to settle a claim by doing something different from the initial
contract. Satisfaction is the
performance of this new agreement.
The court of appeals agreed with the contractor. Since none of this new agreement was in
writing, there must be a new trial over whether the parties had a new deal, and
if so, what it was. Ultimately, the
jury would have to decide this one.
Doug White, a contractor, recently learned the hard way the
importance of a written contract. He assisted
Wanda Pruiett, a homeowner, in pursuing an insurance claim for water damage. He
attended several meetings with the insurance company to evaluate damage and
discussed additional damage that he considered to merit repair.
Pruiett identified White to the insurance representatives as
her contractor to do the repair work.
Ultimately, the insurance company upped its initial offer almost four
fold and agreed to pay the homeowner about $58,500.
After getting the money, the homeowner decided to repair the
home herself. An unhappy White sued for
breach of contract, alleging that he had an agreement with her to be the
contractor. The appellate court decided
otherwise. The case is Doug White v.
Wanda Pruiett, WD 58509 (WD Mo. 2001).
Despite his hard work and input, Pruiett was not legally
bound to do anything with him. Her representations that he would be the
contractor were made to the insurance company, not to him. Most importantly, she refused to execute a
written contract that he sent and she did not sign his bid. In other words, he had nothing in
writing.
James R. Keller is a
partner at HERZOG, CREBS & McGHEE, LLP, St. Louis, Missouri, where he
concentrates on construction law, real estate and business litigation. He is also a panelist with the American
Arbitration Association.