Owner Defenses to Contractor Claims for Nonpayment
by James R. Keller
This article appeared in The St. Louis Bar Journal, p.
16-20, Fall, 2001.
I.
Introduction
Ultimately, owners become the targets in most
construction disputes over the nonpayment of money. After all, by definition and default owners control the cash
flow, deciding who gets paid and when.
This article
examines how owners can defend successfully in a Missouri courtroom their
decision not to pay the original contract price. While emphasizing the owner's perspective, in a breach of
contract case, it also points out to those pursuing payment avenues to consider
when evaluating the legal merit of an owner's decision not to pay. The focus is limited to disputes between
owners and contractors, and between contractors and subcontractors, but the
general principles apply to others, as well.[1]
II.
Missouri's Approved
Jury Instruction
Juries more than
judges decide the significant construction lawsuits and the appellate courts
continue to issue dozens of decisions each year on these trials. This article relies on those cases. (Binding arbitration is beyond the scope of
this article.)[2]
Missouri has an
approved jury instruction for breach of contract construction disputes.[3] To recover, a contractor must show what the
contractor and the owner agreed to do, that the contractor "substantially
performed" the work in a "workmanlike manner", that the owner did not perform
(which usually means did not pay), and that the contractor was thereby damaged.
An owner should
concentrate on defeating one or more of these elements, for they offer an
owner's best chance at success, as more fully discussed below. (Affirmative defenses are not covered.)
A.
Substantial
Performance
1. Defined by case law
Missouri has
several approved jury instructions in non-construction breach of contract
disputes, all of which require proof of full performance to recover.[4] By contrast, a contractor in a construction
dispute only has to prove substantial performance to recover.[5] Complete performance is not necessary. This difference obviously benefits
contractors.
Owners still have
hope, however, as Missouri also has a separate mandatory jury instruction
defining "substantially performed" to mean "performance of all important parts
of the contract with only slight variations".[6] This instruction practically invites an
owner to argue that the contractor did not perform "all important parts" and to
argue that the contractor's deviations were more than slight. (To an owner, every deviation seems
important.) Either argument could
defeat entirely a contractor's claim for more money. Thus, proof of "substantial performance" could be do or die for a
contractor.
The Missouri
courts define substantial performance to be when the owner can use the building
for its intended purpose.[7] This is a fact question to be decided at
trial.[8] However, once an owner occupies the
building, and begins its business operations, it is difficult to argue against
substantial performance.
2. Defined
by Agreement
The American
Institute of Architects (AIA), the industry standard for construction
contracts, defines substantial performance[9],
much like Missouri case law, as occurring when the "owner can occupy or utilize
the work for its intended use".[10] Likewise, many non-AIA
contracts define substantial performance in a similar manner.
Typically, final payment is tied to the
contractor reaching substantial performance.
Thus, anyone involved in a payment dispute over substantial performance
should carefully consider when the owner really could use the construction
project, leaving aside aggravation and a job that is less than perfect. The answer may determine if the contractor
can recover at all, and if so, how much.
3. Slight Deviations
Substantial
performance occurs despite contractor deviations from the contract, or
imperfections in the work, provided they are "slight" or "trivial".[11] Contractor effort is important, especially
if the question of substantial performance is close. At least one court looked for a contractor's "honest endeavor to
comply"[12]. Another observed that it is "highly unusual"
for a project to be in exact accordance with the plans and specifications.[13] This means that an owner needs a real
reason, a substantial complaint, to viably justify nonpayment, due to a
contractor's alleged failure to achieve substantial performance.
4. Owner
Damages or Offset from Payment
Defective work
does not always offer the owner a complete defense, but it does provide at
least a partial defense for nonpayment in full under the contract. Substantial performance entitles the
contractor to recover the contract price, but only after deducting the money
necessary to finish the work and to correct any defects.[14] Thus, an owner should always look at these
costs when considering its defense, with an eye toward developing enough in
repair costs to completely offset or at least reduce the amount of money
otherwise owed.
In rare cases, the
measure of damage to repair or complete work is the diminution in value to the
property.[15] This method applies when the cost to repair
or complete the project involves unreasonable economic waste. The offset or damage then is the difference
between the value of the property as built and as it should have been built.
B. The
Agreement
To recover, the
contractor must prove to a jury the terms of the agreement between the owner
and the contractor.[16] Since the original written agreement often
changes as the work progresses, it may be difficult to determine by the end of
the project what the parties had agreed to do.
An owner often can defend a decision to stop payment based on a dispute
about the terms of the agreement, or because the contractor was not complying
with them. A construction project is a
moving target, a fact that at least initially allows owners latitude in
refusing to pay.
1. The
Jury Instruction
When appropriate,
owners should require that the contractor set forth in the verdict directing
instruction as much detail about the agreement as possible, particularly what
the contractor agreed to do. The
instruction must submit "every essential element" necessary to recovery.[17] Jury instructions require a finding on
"every contested, material issue" or there is reversible error.[18] Because construction projects are complex
and ever changing, owners should "load-up" this instruction with all important,
disputed aspects of the agreement.
In one case where
a subcontractor sued a contractor, it was not enough that the subcontractor had
sufficient evidence at trial to support its claim of substantial performance,
by showing that it supplied glass that was merchantable, of good workmanship,
free from defects, and suited for the intended purpose.[19] Nothing in the verdict directing instruction
required the jury to make these findings, which the contractor contended were a
critical part of the parties' modified agreement. The appellate court agreed and reversed a judgment, due to
instruction error, even though there was no objection to the instruction until
a motion for new trial.
In another case,
the Western District Court of Appeals reversed a judgment for a contractor of
$561,200 on a breach of contract claim, because the verdict directing
instruction did not require the jury to decide whether the contractor had to
perform extra work due to changed conditions.[20] While the evidence at trial supported this
conclusion, without an express finding by the jury, the owner could have
another trial.
2. Scope of Work
All contracts,
whether written or oral, should set out what the contractor is to do, and thus
define the "scope of work". Detail and
clarity are important, and scope of work provisions need to include the
contract's general conditions, as well as the more technical drawings, plans
and specifications.
A contractor who
follows the owner's plans and specifications will not be responsible for
defects.[21] However, an owner certainly can defend a
nonpayment claim when the contractor does not follow the contract, or deviates
from the scope of work. In fact, an experienced
builder has a duty to a layperson owner, given a contract provision calling for
workmanlike construction, not to build pursuant to an owner's documents or
"sketch" if doing so would produce "substantial defects."[22]
The scope of work
often changes, even on small projects.
The accepted practice, when this occurs, is for the owner and general
contractor to execute a written change order, an amendment to the original
contract, outlining this new and different work, and how much money will be
paid for it. Larger construction
projects typically call for many formal change orders covering such topics as
additional time to complete the project, redesign of the project, extra work,
change in product, and the like.
Change orders can
impact a contractor's costs to do the work in ways far beyond the dollar amount
agreed upon in the change order. For
example, if the contract time is extended by one month, the contactor may incur
additional third-party and delay costs for this period, which were not included
initially in the change order. An owner
can defend a claim for such additional costs if the change orders to not
contain a provision to later-request such costs.[23] Many contractors fail to reserve their
rights to additional money, and they regret it later.
3. Retainage
Construction
contracts are unique when it comes to payment.
Typically, they allow an owner to withhold a percentage, often ten
percent, from the amount otherwise due with each cash payment to a contractor. This withheld amount is called "retainage". Upon substantial completion, the owner
usually releases the retainage[24]. An owner's greatest leverage is to withhold
any payment, especially the retainage. Even if otherwise owed, an owner may
decide to withhold payment of retainage to offset money it claims from the
contractor, such as for defective work.[25] Again, he who controls the money, at least
for awhile, controls everything.
Courts will enforce a contract
provision between a contractor and its subcontractor calling for payment of
retainage when the owner pays the contractor.[26] However, Missouri courts also will support
an owners' decision not to release retainage without proper documentation, such
as evidence of final payments to subcontractors, final mechanics' lien waivers,
certificates of completion, a contractor's affidavit, invoices for labor,
equipment and materials, project construction records, and an affidavit of
prevailing wage compliance.[27]
A contractor for the Kansas
City Zoo lost a $454,572 judgment in 2000 because it did not properly
document its claim.[28] The Zoo, as owner, prevailed under
Missouri's Prompt Payment Act because of what many would consider to be
technical requirements for a contractor to provide invoices and other
information.
4. Extra
v. Additional Work
Quite
often a contractor does work that it feels exceeds the scope of the original
agreement, work requiring more time, money, materials or all three. The question becomes whether this is extra
or additional work.
Extra
work is work not originally contemplated by the parties. Additional work is work required to complete
the contract, which arose from conditions the contractor did not initially
anticipate.[29]
An owner can defeat a claim to increase
the contract price if it is additional work, while a properly documented claim
for extra work, to an owner, translates into more money. The fact finder must decide which it is.[30] The scope
of work provision often breaks the tie in close calls.
5. Delay in Completion
Time
is money, for the contractor and for the owner. Thus, no construction article would be complete without some
consideration of a delay-in-completion claim, which often is made by both the
contractor and the owner on the same project.
A contractor who promises to complete the job by a date certain is bound
by this promise.[31] His "unexcused" delay entitles the owner to
damages, another reason an owner can withhold payment.[32] When no time limit is fixed, the law implies
a reasonable time to perform.[33]
There
are many reasons for delay that are not a contractor's fault, but most
contracts require that the contractor, regardless of the reason, notify the
owner of a contractor's request for more time.
Failure to do so can defeat a contractor's claim for more money. In fact, if required in the contract,
written notification becomes a condition precedent to recovery by the
contractor, [34]
and thus a "technical" defense that has teeth.
C. Workmanlike
Most
contracts contain a provision that the contractor perform the work in a
workmanlike manner.[35] Even if the contract is silent on this
requirement, there is an implied warranty, by case law, that every contractor's
and subcontractor's work must be workmanlike.[36] Workmanlike means "work which is completed
in a skillful manner and is non-defective."[37] Bad work, at any stage, can be reason enough
to stop payment, and a defense that owners should automatically consider in
every case.
Proof
that work was not workmanlike may require expert testimony. For example, homeowners could not recover
against their contractor when a large retaining wall collapsed, as "the
question of whether concrete retaining walls are constructed in accordance with
sound engineering principles should be answered by expert opinion testimony".[38] This was beyond the common knowledge of a
judge or jury.
On
the contrary, a trial court could decide, without expert testimony, if the
plaintiff, in a workmanlike manner, filled a lagoon with dirt and then
compressed it with a tractor.[39] Such evidence does not involve
interpretation of technical or engineering principles.
III.
Conclusion
This article merely scratches the surface. The casebooks offer a bounty of fertile ground for those pursuing and those defending owners over the nonpayment of money.
[1] In construction, a dispute between a
contractor and a subcontractor generally requires the same analysis as a
dispute between an owner and a contractor. When considering such claims, the
contractor becomes the owner and the subcontractor becomes the contractor.
[2] Construction claims work well in
arbitration and they comprise a significant portion of the disputes handled by
the American Arbitration Association (AAA), the world's largest forum for
alternative dispute resolution. In
fact, the standard American Institute of Architects (AIA) contract requires
binding arbitration with AAA, General Conditions of the Contract for
Construction, AIA Document A201-1997 Edition, Article 4.6.
[3] M.A.I. 26.07
[1981 Revision]. The instruction
reads:
Your
verdict must be for plaintiff if you believe:
First,
plaintiff and defendant entered into an agreement whereby plaintiff agreed [set out plaintiff's agreement] and
defendant agreed [set out defendant's
agreement], and
Second,
plaintiff substantially performedhis agreement [in a workmanlike
manner], and
Third,
defendant failed to perform his agreement, and
Fourth,
plaintiff was thereby damaged.
[4] See
generally Chapter 26, M.A.I.
For a good discussion on the difference between M.A.I. 26.07 (the
construction instruction) and M.A.I. 26.06 (the non-construction
instruction), see Lindsey Masonry Co. v. Jenkins & Assoc.,
897 S.W.2d 6, 13 (Mo. Ct. App. 1995).
[5] M.A.I. 26.07 [1981 Revision]
[6] M.A.I. 16.04 [1980 New]. The instruction reads: "The phrase 'substantially performed' as
used in this [these] instruction[s] means performance of all important parts of
the contract with only slight variations."
Court opinions offer two reasons why substantial performance is enough:
First, an owner still receives benefit for work performed, even if rejected,
since such work typically cannot be returned to the contractor. Thus, it is "equitable" to require payment
for work received. Second, it is
virtually impossible for a contractor to comply completely with all the
detailed specifications for a building contract. Cross v. Robinson,
281 S.W.2d 22, 24 (Mo. Ct. App. 1955).
[7] Southwest
Engineering Co. v. Reorganized School Dist. R-9, 434 S.W.2d 743, 751
(Mo. Ct. App. 1968).
[9] AIA uses the phrase "substantial
completion". General Conditions of the
Contract for Construction, AIA Document A201 - 1997 Edition,
Article 9.8.1.
[11] McAlpine Co. v. Graham, 320 S.W.2d 951, 954 (Mo. Ct. App.
1959).
[13] Lindsey
Masonry Co. v. Jenkins & Assoc., 897 S.W.2d 6, 13
(Mo. Ct. App. 1995)
[14] Ken Cucchi Const., Inc. v. O'Keefe, 973 S.W.2d 520, 524 (Mo. Ct. App. 1995).
[15] County Asphalt Paving Co. v. The 1861 Group, Ltd., 908
S.W.2d 184, 186 (Mo. Ct. App. 1995)
[17] E.A.U.,
Inc. v. R. Webbe Corp., 794 S.W.2d 679, 687 (Mo. Ct. App. 1990)
[20] Environmental
Protection, Inspection and Consulting, Inc. v. City of Kansas City, 37
S.W.3d, 360, 368 (Mo. Ct. App. 2000).
[21] U.S.
v. Spearin, 248 U.S. 132 (1918).
[22] Waldroup
v. Dravenstott, 972 S.W.2d 364, 369 (Mo. Ct. App. 1998).
[23] Uhle
v. Tarlton Corp., 938 SW.2d 594, 599 (Mo. Ct. App. 1997)
[24] "Retainage has to do with the time of
payment, not the cost of construction."
Wisch & Vaughan Const. v.
Melrose Prop., 21 S.W.3d 36, 43 (Mo. Ct. App. 2000)
[25] Herbert
& Brooner Const. Co. v. Golden, 499 S.W.2d 541, 544 (Mo. Ct. App.
1973).
[26] Woodman
Engineering Co. v. Licking Const. and Dev. Corp., 786 S.W.2d 178, 182
(Mo. Ct. App. 1990).
[27] Environmental
Protection, Inspection and Consulting, Inc. v. City of Kansas City,
37 S.W.3d 360, 370-71. (Mo. Ct. App. 2000).
[29] Gilmartin
Bros., Inc. v. Kern, 916 S.W.2d 324, 331 (Mo. Ct. App. 1995).
[30] Wisch
&. Vaughan Const. v. Melrose Prop., 21 S.W.3d, 36, 40
(Mo. Ct. App. 2000)
[31] Herbert
& Brooner Const. Co. v. Golden, 499 S.W.2d 541, 549 (Mo. Ct. App. !973).
[33] Artcraft
Cabinet, Inc. v. Watajo, Inc., 540 S.W.2d 918, 925 (Mo. Ct. App. 1976).
[34] Southwest
Engineering Co. v. Reorganized School Dist.
R-9, 434 S.W.2d 743, 750 (Mo. Ct. App. 1968).
[35] See
Article 3.5, AIA Document A201-1997
[36] Baerveldt
& Honig Const. Co. v. Szombathy, 289 S.W.2d 116, 118
(Mo. 1956).
[37] Jake
C. Byers, Inc. v. J.B.C. Investments, 834 S.W.2d 806, 818 (Mo.
Ct. App. 1992); Evans v. Werle,
31 S.W.3d 489, 491 (Mo. Ct. App. 2000).
[38] Biggerstaff
v. Nance, 769 S.W.2d 470, 473 (Mo. Ct. App. 1989)
[39] Jake
C. Byers, Inc. v. J.B.C. Investments, 834 S.W.2d 806, 818-19 (Mo. Ct. App.
1992).