CONTRACTOR HITS HOME RUN IN BALL FIELD TOPSOIL DISPUTE
by James R. Keller
This article appeared in St. Louis Construction News &
Review, p. 9, January-February, 2002.
The Forsyth R-III School District recently discovered that
dirt is not dirt cheap. The case is Textor
Construction v Forsyth R-III, Case No. 23744 (Mo.App. S.D. 2001), decided
October 11, 2001.
The dispute was over missing topsoil for the District's ball
fields. The appellate court,
interpreting conflicting provisions in a modified AIA contract, upheld a
contractor's claim to recover more money for grading work on the fields, even
though the District claimed "foul" because the contractor did not provide the
topsoil or complete the job on time.
Further, the District could not recover liquidated damages
for the contractor's 84-day delay in completion. Apparently, the architect's representative told the contractor
"on several occasions" that the District waived this claim due to its own delay
in timely starting the project. Thus,
the contractor concluded that it was not required to file a written request for
an extension of time. The appellate
court agreed.
The appellate court ordered the District to pay Textor an
additional $38,000 for work under the contract. The District's only consolation was that it did not have to pay
interest on this $38,000.
The appellate court decided that the trial court erred in
awarding interest under Missouri's Prompt Payment Act, 34.057.1(8). The Act requires that before an owner has to
pay statutory interest for late or non-payment, the contractor must show at
least one of several events. One of
them is that the architect certified the project as complete, "including the
filing of all documentation and certificates required by the contracts in
complete and acceptable form."
Textor could not show this.
In fact, this requirement snares many contractors, even those who
ultimately recover more money that the owner had improperly withheld.
Both the trial and appellate courts concluded that Textor
should receive, by contract, another $38,000, and the District should not have
withheld this money. However, the
architect did not issue the final certificate of payment (as specified under
Missouri's Prompt Payment Act). Hence,
interest, initially awarded by the trial court at 18%, was not
recoverable. This case reinforces the
importance of following exactly the requirements of the Prompt Payment Act
before a contractor can recover interest, even on money otherwise due.
The appellate decision also points out the problems when a
contract contains conflicting scope-of-work requirements. The contract, before modifications, was an
AIA "Standard Form of Agreement Between Owner and Contractor where the Basis of
Payment is a Stipulated Sum." The
general specifications provided for four inches of topsoil, if necessary, to be
furnished by the contractor. Another
provision, labeled an Addendum, stated that it superceded other
provisions. It required that the ball
fields "can be lowered as required to avoid bringing in any fill dirt."
The court resolved this conflict by enforcing the Addendum,
on the basis that the contract's more specific language trumped the general
language in the specifications. Given
this finding, the architect had misconstrued the contract by not certifying
payment of the remaining $38,000 to Textor as final payment.
In reaching this decision, the court also considered that
the District had intended to install an irrigation system, with someone other
than Textor, after Textor left the job but before topsoil was placed on the
site. The court interpreted this action
as evidence that the contractor was not required, initially, to place topsoil
on ball fields that would then be torn up to install this irrigation
system.
The District had counter-sued, alleging delay damages,
failure to substantially perform, and that the contractor had never requested,
much less received, a time extension.
The District claimed $79,000 for the missing topsoil, which after
deducting the $38,000 owed to Textor, left the District with damages of
$40,950. The court concluded
otherwise.
The District struck out on its claim for liquidated damages
because of the statements from the architect's representative to the contractor
that the District waived the claim.
Assuming the parties had a typical AIA contract, it would have required
that modifications to it had to be in writing.
Regardless, the court noted that parties to a contract, through their
actions, can modify or waive its provisions, even those in writing, and this is
exactly what happened in this case.
Contractors and owners often make oral changes to their
written contract as work progresses, sometimes on a daily basis. If every change had to be in writing, many
projects would never be completed on time.
Perhaps some would never be completed at all. This case offers caution that such conduct, while widely
practiced in the construction industry, may have serious adverse legal
consequences.
James R. Keller is a partner at HERZOG, CREBS & McGHEE,
LLP, where he concentrates his practice on construction law and business
litigation. He also is an arbitrator
with the American Arbitration Association and a court-certified mediator.