Homeowners Defeat Contractors in Two Cases
by James R. Keller
This article appeared in St. Louis Construction News &
Review, p. 10, November-December, 2002.
Missouri homeowners scored two recent and significant
appellate court victories on issues homeowners frequently face.
In one case, the Eastern District Court of Appeals decided
that a homeowner could sue her contractor seven years after moving into the
house. Missouri's five-year statute of
limitations for breach of contract did not start until the homeowner knew of
serious structural defects. Prior,
minor punch-list items were not enough to trigger an earlier date. The case is Allen v. Kuehnle and Kuehnle Bros. Const. Co., No. ED 80727,
decided October 8, 2002.
This result continues to lengthen the potential exposure and
liability of all contractors. There now
is a clear court trend in this direction.
In the other case, the Southern District Court of Appeals
decided that homeowners could recover their costs to repair after their
contractor walked off the job. This
case is Erney v. Freeman d/b/a Phil's
Custom Const., 84 S.W.3d 529 (Mo. App. SD 2002), decided September 19,
2002.
In Allen, the home
was to occupy a quarter of the "footprint" of ground excavated by the
contractor during removal of the prior house.
After moving into the completed home in May 1993, the homeowner noticed
various problems, prompting a punch list dated August 24, 1993.
The punch list contained 26 items including hairline cracks
in the drywall, drywall tape pulling away from walls in certain places, two
sections of the sidewalk that sloped, and some loose shingles. The contractor repaired or attempted to
repair most of the items on the punch list.
In 1998, the homeowner began to notice "numerous new, more
dramatic problems with her home," such as cracks in the foundation and exterior
brick walls, a huge L-shaped crack in the family room, and drywall tape that
was pulling away from the walls in nearly every room.
The homeowner decided to have her home piered, per an engineer's
advice. This process generated
considerable dust and debris. While
cleaning the dust, the homeowner developed a sore on her foot that became
infected. This resulted in a hospital
stay and medical costs of $3,667.
Allen sued in November 1999, claiming breach of contract,
negligence and a recission of the contract.
The contractor defended, in considerable part, on the grounds that Allen
had waited too long to sue, given Missouri's five-year statute of limitations.
He argued that the homeowner knew of structural problems
with the home more than five years before she filed the lawsuit. The trial judge agreed and granted summary
judgment for the contractor, deciding that a trial was not necessary.
Missouri's statute of limitations requires the filing of a
lawsuit within five years of the date when damages are sustained and capable of
ascertainment. However, as the
appellate court noted by citing Business
Men's Assurance Co. of America v. Graham, 984 S.W.2d 501, 507 (Mo. 1999),
the phrase "capable of ascertainment" has never been given a precise
definition.
The issue was whether the punch list created in 1993 and the
homeowner's knowledge about problems before 1995 were enough to provide notice
to the homeowner of the structural problems.
There was contradictory evidence on this point.
The appellate court concluded that material facts were still
in dispute as to when structural problems were ascertainable; thus, the trial
judge erred by granting the motion for summary judgment. By law, a summary judgment must be based on
facts that are not in dispute.
In distinguishing other cases, the appellate court found the
compelling difference to be that the homeowner's problems before 1998 were not
problems related to settlement or faulty soil compaction. Rather, the prior problems were typical,
common issues experienced during the construction of a new home.
The court relied heavily on the recent Missouri Supreme
Court decision in Business Men's
Assurance. In this case the
chipping and falling of small pieces of marble from the side of a building in
the 1960s was not enough notice to prevent a lawsuit when entire marble panels
were falling off the building in 1985.
In Erney,
homeowners had hired a contractor to finish their basement. The contract contained a one-year express
warranty for workmanship after completion.
The homeowners filed a lawsuit contending that their
contractor breached the contract by providing poor workmanship. The contractor counter sued, alleging that
the homeowners breached the contract by refusing to allow the contractor to
complete the work.
The appellate court determined that the contractor had
breached the contract by not correctly installing insulation and by not
providing proper electrical wiring, including wiring in compliance with federal
and local codes. After learning of the
problems during construction, the homeowners offered the contractor two
options.
First, the contractor could stay on the job but the
homeowners would select the subcontractors to complete the insulation and
electrical work. Second, the contractor
could return part of the payment received and the parties would "call it even,
and go our separate ways."
The contractor rejected these options with an emphatic "no,"
walked off the job and never returned.
The contract did not provide the contractor with a right to
cure. Thus, the appellate court
concluded that the owners did not have to give the contractor an opportunity to
repair or correct the defects before filing a lawsuit for breach of contract.
When a breach results from a combination of defective
construction and a failure to complete the work, the owners' damages are
calculated using the reasonable cost of reconstruction, repair and completion
in accordance with the contract. By
adding the homeowners' payments made to the original contractor to the
additional payments made to the contractors hired to finish and repair the
work, and then subtracting the original contract price, the difference--in this
case $10,995-is the damage that the homeowners can recover from the original
contractor.
James R. Keller is a partner at HERZOG, CREBS & MCGHEE,
LLP, St. Louis, Missouri, where he concentrates on business litigation and
construction law. He also is a
neutral/arbitrator with the American Arbitration Association, a court-certified
mediator in federal court and on the list of approved mediators in state court.