Contractors Recover for Extra Work Without Written Change Orders
by James R. Keller
This article appeared in St. Louis Construction News &
Review, p. 58, March-April, 2003.
In two recent appellate decisions, Missouri's Eastern
District Court of Appeals in St. Louis has upheld awards for extra work
performed without written change orders, even though the contracts called for
written change orders. The cases are Flooring Systems, Inc. v. Staat Construction
Co., ED 80814 and ED 80867, filed February 11, 2003, and The Missouri Dept. of Transportation, ex
rel. PR Developers, Inc. v. Safeco
Insurance Co. of America and Robertson Contractors, Inc., ED 79860, filed
November 5, 2002.
These cases reinforce that contractors and subcontractors
can, under certain circumstances, recover when they perform extra work beyond
the scope of the original contract, but they do not have anything in
writing. Virtually every project in the
construction industry involves some sort of oral agreement or conversation
about extra work. These cases offer
important guidance to everyone about which unwritten extra work claims are
viable in Missouri and which claims will fail.
In Flooring Systems,
the trial court found that the contract "contemplates" that any change to the
original plan was to be made as a written change order, submitted by the
architect and signed by the owner and the contractor. The project involved site improvements and construction of
buildings for an office complex for a guaranteed maximum price of $1,600,252.00.
Staat Construction, Inc. was the general contractor. The owner and Staat met frequently during
construction to discuss the progress of the job. These discussions included changes in the original plans as
circumstances dictated, such as storm water run-off and detention, site
grading, parking, a retaining wall, type of brick to be used, use of aluminum
soffit, and tenant-finish issues.
The lawsuit involved a number of issues including Staat's
claim against the owner for compensation for extra work. The owner defended on the basis that Staat
breached the contract by not submitting any written change orders or providing
notice of cost overruns to the guaranteed maximum price for the contract.
The case was tried before a judge who found that the
requirement of written change orders had been waived by the actions of the
owner and the contractor. To establish
a waiver, the contractor has to prove either habitual acceptance of work
completed upon oral change orders or that the owner and contractor agreed
orally to the changes and the changes were then completed by the
contractor.
During construction, Staat had discussed with the owner the
many changes that took place and received oral approval for them. Also, the owner accepted the extra work performed
by Staat. Given this course of conduct,
the appellate court agreed that Staat was entitled to $154,831.06 for extra
work and its construction manager's fee.
In Missouri Department
of Transportation, PR Developers, a subcontractor, sued its general
contractor for breach of contract and the general contractor's surety for
vexatious refusal to pay. The project
was construction of a bridge, embankments, ramps and roadways at the
interchange of Interstate Highway 55 and Routes H and HH for the Missouri
Department of Transportation. PR
Developers was the subcontractor for the base rock and paving portions of the
job.
The case was tried before a jury and involved a number of
issues, including PR Developers' claim for compensation for extra work. The jury awarded PR Developers $74,810.16
for non-delay damages and $1,581,192.50 for delay damages.
The trial judge instructed the jury that it should return a
verdict for PR Developers on its claim for extra work if it believed that the
general contractor and PR Developers had agreed that PR Developers would
perform certain "tasks" outside the scope of the written subcontract and
Robertson, the general contractor, would pay PR Developers for the work.
PR Developers also had to prove that it performed the work
and that Robertson failed to pay for it.
The general contractor argued at trial that the judge should
not have instructed the jury as it did because the contract required specific
written authorization for extra work before the subcontractor can recover
additional money and because PR Developers did not establish that the general
contractor had waived this provision.
There was scant evidence of "habitual acceptance" of work
being done through oral change orders.
However, P. Mitchell Parris, president of PR Developers, testified that
Robertson had asked for equipment and labor from PR Developers to repair the
bridge approach slab, additional rock for a sub grade and that PR Developers
hire a trainee to help Robertson meet its requirements for using trainees on
the project. All of this work was
outside the scope of the written contract.
Parris' testimony was enough to prove an oral agreement and
hence a waiver of the requirement of written change orders. The appellate court upheld the jury's award
on this claim.
James R. Keller is a partner at Herzog, Crebs & McGhee,
LLP, St. Louis, MO, where he concentrates on business litigation, construction
law and ADR. He also is a
neutral/arbitrator with the American Arbitration Association and a
mediator.